WCID begins work on spillways
Last month, the Lower Brushy Creek WCID began work to repair principal spillway pipes on three of the rural dams in the district.
“The principal spillway pipes carry flood water from the lake to a plunge pool downstream,” explained Jim Clarno, general manager of the district. "At these three dams, the last section of pipe has separated from the upstream pipe due to 50 years of deterioration of he pipe supports.”
Two of the principal spillways need a pipe liner to eliminate leakage into the pipe. The plunge pools at all three dams will be reshaped, trees and brush removed and will be rock rip-rapped.
The sites being worked on include
Site 3 north of Thrall,
Site 10 northeast of Thrall, and
Site 30 just west of TX 95 between Taylor and Coupland.
The work began July 13 and is expected to be substantially completed by Sept. 11, with final completion Oct. 11.
“The schedule is dependent on weather so substantial and final completion could be delayed,” Clarno said.
The total cost of the project is $948,000. All the funds for this project are from the district’s own revenues. No state or federal grant funds will be used.